The planning and execution of our
greenhouse/solar panel structure has been complex. We needed to shift
installation companies, apply for retro-active permits, and build the
structures during the hottest summers on record. It was a whole summer project,
which has just wrapped up last week.
Because of rebates, a real concern about climate change,
striving for the Georgetown Energy prize, and peer pressure, solar panel
installation is way up in Corvallis this year. In March, solar companies were
seeing a ten fold increase in the number of people interested in installation
and that continued throughout the summer. All of the companies in town were
booked out early. We worked with Benton Electric, who was able to reach further
afield for teams, but the press of business made communication difficult, which
had long term impacts on the permitting process.
In late June, we worked with
Benton Electric to begin the process. They calculated that eight panels,
creating a 2.2 kw system, should cover our use for the year, if we were
conservative. Nine would be better, but they would block considerable light
into the greenhouse, and we decided against the extra panel. Once we had the
dimensions for the layout of the panels, our builder went to work constructing
the greenhouse and panel rack. It is an uneven hexagon, a bay with windows of
three different sizes projecting into the yard, with a long annex that reaches
all along the neighbor’s garage. Because of the design, it does not dominate
the view of the gardens, but blends in, even without mature plantings. For
days, he dug deep post holes and planted the treated beams that would hold the
structure upright. Once they were all planted, he needed to cut the roof
angles, all different because of the shape. When the angles were cut, he had
down the roof and framed in the windows, then hung them, and framed them in
with cedar. Once the greenhouse was finished, we painted the clawfoot tub and
moved it in, setting up the shower.
When the greenhouse was complete,
Mark, our builder, moved onto the rack for the panels, which is also a funky
structure of angles and braces, raising the panels thirteen feet above the
ground for maximum light and minimal visual intrusion. He finished the evening
before the panels were to be installed. The next day, in early August, the
installers arrived. “That’s interesting,” the head installer commented, “but I
can work with it.” In four hours, they had installed the panels, wired the
system in, and added an outlet in the greenhouse. We were on track for completion, just waiting on the electric
installation….
And then things came to halt. The
electrical inspector, seeing the structure and thinking “that’s weird” referred
us for a building permit before the electric could be inspected. “But we don’t need a permit,” I argued, “the
structure is too small.” “Code says that you do,” the city returned. What code?
We don’t know. What did we do wrong? We don’t know. One person talked about
earthquakes, another about hurricane force winds. Maybe we should cement the
posts in, even though that rots them faster….it was never really clear. Don’t
ask, was the general message. Hire a structural engineer to write a letter
saying that the whole plan is ok. It will be easier than bringing it up to
building code. So we did. “Humrph,” he said. “That’s interesting. Lets put a little brace in here and call it
good.” “A trellis? I can live with a trellis.” Several weeks later, we received
the retroactive permit and passed the electric inspection. But the panels were
still not on.
Pacific Power needed to replace
our meter—and Benton Electric needed to repair a fuse so that the system
worked. That added another week to the whole process….finally, I came home to a
new meter. Two days later, to a functional system. The meter was spinning
backwards! For the first week, we produced four to five kwh per day; when the clouds went away,
production went up to six, then seven, and today, eight. We are at the equinox,
with the sun sliding down in the sky further every day, so production will
slowly drop off for winter.
So, what did we learn from the
process? Perhaps to ask very specific questions before building—despite talking
with three city departments, we did not know that we needed permits for the
structure that attaches the panels to the greenhouse. Now that we are done, we
are working to live within our means, to not use any more electricity that we
will produce, even if we are not always using fresh electrons.
Fish Pie
This is a layered dish.
Layer one: finely diced carrots
and celery to cover the bottom of the dish, followed by .25 pounds of various
fish—shrimp or scallops, salmon, and white fish. Scraps are good.
Layer two: 1.5 cups of white
sauce, with leeks, salt and pepper.
Layer three: mashed potatoes for
a crust.
Bake until bubbly in a 350 degree
oven.
These Top Solar Companies In Chennai truly live up to their reputation! Exceptional service, cutting-edge technology, and a commitment to sustainability. The installation was seamless, and I'm already experiencing the benefits. Grateful for their expertise in harnessing solar power. Highly recommended for anyone seeking reliable and efficient solar solutions in Chennai!
ReplyDelete